Question Details
[solution] » Can someone please check this work and answer number 9
Description
Answer Download
The Question
Can someone please check this work and answer number 9
Running head: PROJECT ANALYSIS 1 Use the project network, baseline time-phase budget and status information below to answer questions in this problem
set. Baseline (PV)
Budge
Task DUR ES LF SL t (PV) 0
A
2
0 2
0
B
3
2 5
0
C
1
2 6
3
D
2
2 5
1
E
1
5 6
0
F
2
4 7
1
G
3
6 10 1
H
4
6 10 0
I
3
6 10 1
J
2
10 12 0
Period PV Total
Cumulative PV Total 100
200
200
200
100
600
600
800
600
600 25 1 2 3 4 5 6 7 8 9 200
200
100 100
200
400 300
200
100 200 10 11 75
50 100 50
200
150 50
300 25
25 100
300 300 300
75 400 150 350 400 500 700 600 200 300 300
100 500 650 1000 1400 1900 2600 3200 3400 3700 4000 12 Section I
Based on the data provided in the Period 4 Status Report below answer the questions in this section. Status Report Ending Period 4
Task %
EV AC PV
Complete
A
100%
150 150 75
B
50%
40 80 65
C
75%
37.5 100 87.5
D
50%
62.5 125 87.5
E
0%
0
F
0%
0
G
0%
0
H
0%
0
I
0%
0
J
0%
0 CV
0
40
62.5
62.5 SV
75
25
50
25 After period 4, what is the Planned Value (PV) of the worked schedule for Task A (round answer to two
(75+65+87.5+87.5)= 315
2. After period 4, what is the Earned Value (EV) for Task D (round answer to two decimal places)?
(150+40+37.5+62.5)= 290
3. After period 4, what is the Cost Variance (CV) for Task B (round answer to two decimal places)?
Budgeted-cost
40+62.5+62.5= 170
4. After period 4, what is the Schedule Variance (SV) for Task C (round answer to two decimal places)?
75+25+25+50=175
1. Section II
Based on the data provided in the Period 8 Status Report below answer the questions in this section. Status Report Ending Period 8 Task % Complete
A
100%
B
100%
C
100%
D
100%
E
100%
F
100%
G
100%
H
45%
I
15%
J
0%
Cumulative Totals EV
100
200
200
200
100
600
600
360
90
0
2450 ACPV
CV
150 100
140 200
110 200
260 200
120 100
520 600
700 300
100 400
100 500
0
0
2200 2600 SV
-50
60
90
-60
-20
80
-100
260
-10
0
250 0
0
0
0
0
0
300
-40
-410
0
150
- After period 8, what is the Scheduling Performance Index (SPI) value (round answer to two decimal
places)?
SPI=BCWP/ BCWS
2600/250=10.4
6. After period 8, what is the Cost Performance Index (CPI) value (round answer to two decimal places)?
CPI=BCWP/ ACWP
2450/2600=0.94
7. After period 8, what is the Percent Complete Index based on Budget Amounts (PCI-B) (round
answer to two decimal places)?
BAC= total PV for the project
(2600/2200)=1.18
8. After period 8, what is the To Complete Performance Index (TCPI) (round answer to two decimal
places)?
TCPI= (BAC-EV)/ (EAC-AC)
(2600-2450)/ (2450-2200) =0.6
9. After period 8, what is the forecasted Estimated Total Cost at Completion (EACf) (r round answer to
two decimal places)? (Hint: use the forecasting method)
10. Estimate at Completion = (Budget at Completion) / (Cost Performance Index)
(2450/ 0.94) =2606
11. After period 8, what is the forecasted Variance at Completion (VACf) (round answer to two decimal
places)? (Hint: use the forecasting method)
Variance at completion=BAC-EAC
2600-2450= (150/2600)*100=5.7%
5. Section 3 You have been provided with the following revised estimates for the remainder of the project: Activity H will be completed at the end of period 12 at a total cost of 600 Activity I will be completed at the end of period 12 at a total cost of 750 Activity J will be completed at the end of period 14 at a total
cost of 500 Use the above revised estimates to answer the questions
in this section.
Base on the revised estimates, what is the Estimated Total Cost at Completion (EACre) (round
answer to two decimal places)? (Hint: use the revised estimate method)
Total cost of completion=budget at completion/ cost performance index
(2600+600+750+500)/0.94= 4734.04
13. Base on the revised estimates, what is the Variance at Completion (VACre) (round answer to two
decimal places)? (Hint: use the revised estimate method)
12. Variance at completion=BAC-EAC
(4450-2450)/2450= (2000/ 4450)*100=44.94% Section 4 Use the information provided below to compress one time unit per move using the least cost method. Reduce the
schedule until you reach the crash point of the network. Table 2 Activity ID
A
B
C
D
E
F
G
H Activity
Predecessor
None
None Crash
Cost
(Slope
125
225
B 150 A, C
A, C E, F, G Max
Crash
Time 50
-B 300
D 100
200 Normal
Cost
2
2
3
1
0
3
2
3 2000
4000
2500
1000
5000
3000
500
1000 Normal Time
(days) 5
4
7
2
3
8
5
6 What is the direct cost of the project after the project is crashed using the least cost method to
duration of 18 days (round answer to two decimal places)?
Normal cost= (2000+4000+2500+1000+5000+3000+500+1000) =19000
Crash cost = (125+225+150+50+300+100+200) =1150
Direct cost= normal cost-crash cost= 19000-1150=17850
15. Which activities do you need to crash to get to the crash point of the network?
Activities to be crashed are activities F and C
16. What is the duration (in days) of the project after the project is crashed to the crash point of the network?
= 5+4+7+2+3+8+5+6=40-3= 37 days.
14. Section 5 Table 3 below provides the direct and indirect costs incurred by an IT project for various
project durations. Use this information to answer the questions in this section.
Table 3
Project Duration
(in days) Indirect Cost
Direct Costs 57
54
50
48 3200
3400
3550
3850 1100
1050
1000
950 Given the data provided in Table 3, should the project be crashed? Project should not be
crashed since the actual normal cost and budgeted cost is the same therefore no amount
will be saved upon crashing the product (Bartlett, 2004).
18. If the project?s client was willing to pay $100 for each day the project was delivered
early to the 48th day mark, what day would you crash the project to?
Total anticipated cost =100*48= 4800
Total actual cost= 3850+950=4800
17. Section VI
Use the information provided below to answer the question in this section.
Assume your project team has identified two factors that significantly affect the project?s
probability of failure, degree of integration (Pi) and number of units involved (Pn); where the
probability of Pi and Pn are 0.30 and 0.45, respectively. They have also identified the following
five consequences: time (Ct), budget (Cb), quality (Cq), external stakeholder satisfaction (Ce),
and internal stakeholder satisfaction (Ci). They have determined the value of these
consequences as follows: Ct= 0.20, Cb= 0.40, Cq= 0.30, Ce= 0.30, and Ci = 0.10.
Based on a calculated risk factor (RF), how would you classify the risk (Low RF < 0.30,
Medium RF 0.30 to 0.70, High RF > 0.70)?
Time= 0.30*0.2 +0.45*0.20=0.14 the risk factor is low.
Budget=0.45*0.4 +0.30*0.4=0.4 the risk factor is medium.
Quality= 0.30* 0.3+0.45*0.0.3=0.225 the risk factor is low.
External stakeholder function=0.3*0.3+0.3*0.45=0.225 the risk factor is low.
Internal stakeholder=0.1*0.3+0.3*0.45=0.155 the risk factor is low.
19. s Section 6
Solution details
Solution #000176287
Pay using PayPal (No PayPal account Required) or your credit card . All your purchases are securely protected by .
About this Question
STATUSAnswered
QUALITYApproved
DATE ANSWEREDOct 14, 2020
EXPERTTutor
ANSWER RATING
BEST TUTORS
We have top-notch tutors who can do your essay/homework for you at a reasonable cost and then you can simply use that essay as a template to build your own arguments.
You can also use these solutions:
- As a reference for in-depth understanding of the subject.
- As a source of ideas / reasoning for your own research (if properly referenced)
- For editing and paraphrasing (check your institution's definition of plagiarism and recommended paraphrase).
STUCK WITH YOUR PAPER?
Order New Solution. Quick Turnaround
Click on the button below in order to Order for a New, Original and High-Quality Essay Solutions. New orders are original solutions and precise to your writing instruction requirements. Place a New Order using the button below.
WE GUARANTEE, THAT YOUR PAPER WILL BE WRITTEN FROM SCRATCH AND WITHIN A DEADLINE.
